Road Runner Park Restroom - EVMWD Plan Check complete - Drawings being updated for City permit 
Willdan engineering all POA parking lots - repavement project - bid documents released May 2019, bids due mid July 2019
Goetz Road Block Wall - Permits obtained - Construction Contract Awarded
May 2019 Start, est. September 2019 Completion
View Current Project Fact Sheet (PDF)
Erosion remediation North Causeway
Additional cameras at points of sale/food service/ - Lodge Scheduled September 2019
Additional cameras throughout community - Equestrian Center, Holiday Harbor, Indian Beach Campground next
Lodge remodel - Interior design drawings complete - Construction drawings in progress
Researching Solar Consultants and providers
Golf course lake renovation - Architect selected, design complete - RFP to be released July 2019
Mailbox replacement - Approximately 90% complete 
View Current Project Fact Sheet (PDF)
Led lighting conversion throughout community
Sierra Park North/ Pump Track conceptual planning - Master plan In design - Back in Engineering
Pool Deck Replacement - Scheduled for Winter 2019-2020
Remodel front gatehouses - add missing windows and FRP lined walls - Permit obtained, Windows done, FRP next
Eastport Monument Signage - Survey and Easements in progress
Estates Monument Signage - Survey and Easements in progress
Replace Country Club - Golf Course Signage on Railroad Canyon Road - Permit approved, construction scheduled for July, 2019
Lighting for Roadrunner Park Volleyball Court (LED Solar) - Scheduled for August
Storm Drain Rehabilitation
Electronic message boards - all exit lanes at three gates - same purpose as current banner holders - events, notifications
POA Scanning project - convert 4,800 tract and lot files to electronic - recover much needed office space
Spash Pads - Exploratory, meeting with Health department and vendors to place at pool area
Install propane tank and pump system to sell propane to members at Happy Camp - Permits obtained, scheduled July 2019
Happy Camp Second Phase remodel restrooms and relocate office to the lower road
Happy Camp Docks - Board Approaval 4/2/2019 - Docks to be installed August 2019
Indian Beach and Sierra Park Shade Structures
Improve access to north ski docks - Board Approved in May, scheduled July 2019
All gates Entry and Exit LED Signage - Scheduled July 2019
Small Dog Park (Eastpost Park) redo - Slated to go back to Committees 
East Bay electronic boat speed monitoring