Pavement Project

Locations In Progress

  • Lodge

Locations Completed

  • Blue Bird Hall
  • Canyon Lake Golf & Country Club (parking lot complete, landscaping in progress)
  • Diamond Point Park
  • Eastport Park
  • Equestrian Center Driveway Entrance (pavement complete, landscaping in progress)
  • Gault Field
  • Holiday Harbor Park
  • Indian Beach
  • Moonstone Beach
  • North Ski East & West 
  • Operations Yard
  • Senior Center
  • Sierra Park
  • Canyon Lake Drive North (from Vacation Drive to Goetz Road)

Project Photo Album

Pavement Project

Project Updates

  • Senior Center Parking Lot | May 18 - May 20
     The Senior Center parking lot is also scheduled to start on May 18. Vehicles (including motorcycles) that are currently parked in this lot will need to be temporarily moved by Sunday, May 17. There is additional motorcycle parking at Eastport and North Gate. Vehicles may return to this lot beginning May 21.
  • North Ski Area Parking Lot | May 18 - May 20
    Work is scheduled in the North Ski Area parking lots May 18 through May 20. The east parking lot (launch ramp parking lot) is closed May 18 through 19, it will reopen on May 20. The west parking lot is closed May 19 through May 20, it will reopen on May 21.
  • Parking Notices | May 18 - May 21
    No Parking on Vacation Dr. to Clear Water Dr. May 18 - May 19 and No Parking on Clear Water Dr. to Goetz May 20 - May 21.
  • East Gate Work | May 20 (rescheduled)
    The East Gate exit lane and oversized vehicle entrance lane will be closed on Wednesday, May 20 from 9 a.m. to 5 p.m. as pavement work takes place on this portion of Canyon Lake Drive North.
  • May 6, 2020
    Lodge ADA Ramp WorkWork on the Lodge ADA ramp will begin on Thursday, May 7. Access to the most eastern rental dock will be limited during working hours which are Monday through Friday from 7 a.m. to 5 p.m. for the first 10 days. This ramp is part of Phase 4, however, work in other areas of the parking lot that are part of Phase 3 continues.
  • March 31, 2020 | Canyon Lake Drive Work Begins
    Work will begin on Thursday, April 2 on Canyon Lake Drive from Vacation Drive to Goetz Road. Minimal traffic disruption is anticipated, please follow any posted signs.
  • March 27, 2020 | Lodge Parking Lot Update
    Commercial construction is considered critical infrastructure, so the Lodge parking lot work is continuing. Phase 2 started this week and due to weather delays this phase is anticipated to be completed by April 17. As a reminder, the Lodge parking lot is being split into phases with the goal of keeping portions of the parking lot open at all times. View Lodge Parking Lot Project Fact Sheet (updated). 
  • January 29, 2020 | Lodge Parking Lot Schedule
    One of the largest parts of this project, the Lodge parking lot, will begin on February 10. The parking lot renovation is being split into four phases with the goal of keeping portions of the parking lot open during the renovation. View Lodge Parking Lot Project Fact Sheet
  • January 27, 2020 - January 31, 2020 | Eastport Parking Lot
    Eastport Parking Lot, entire parking lot will be closed (mailboxes will be accessible) 
  • December 16, 2019 | Holiday Harbor & Sierra Park
    Holiday Harbor and Sierra Park were completed last week, and both parking lots are open. Work continues at multiple locations, however, there are no closures scheduled for this week. 
  • December 9, 2019 | Sierra Park
    Sierra Park's parking lot is scheduled for Thursday, Dec. 12 and Friday, Dec. 13. The entire parking lot will be closed during this time. 
  • December 6, 2019 | Holiday Harbor Park
    The weather the past week has affected the schedule. Holiday Harbor has been rescheduled for Dec. 9 through Dec. 13. During this time, the entire parking lot is closed. 
  • November 15, 2019 | Update
    Work continues to progress with the large-scale pavement project. Below is the schedule of upcoming work that will affect parks: Nov. 18 - Nov. 21: Diamond Point Park, entire park closed Dec. 2 - Dec. 5: Holiday Harbor, entire parking lot closed Dec. 4 - Dec. 6 Gault Field Parking Lot, parking lot and fields closed
  • October 25, 2019 | Country Club Parking Lot
    The Country Club parking lot repavement is now complete. The parking lot was reconfigured and repaved. There is now a new more efficient layout with accessible parking near the entrance. New decorative stamped concrete was added to the Country Club entry and drive circle. New LED parking lot lights were also installed. 
  • September 23, 2019
    Project started with setup at East Port Park. 
  • August 2019
    Final vendor selected - Board approved funding for this project in an amount not to exceed $3,425,000
  • July 2019
    Request for Proposal closed, three bids received ranging from $3,400,000 to $4,600,000
  • June 2019
    Request for Proposal Published

Project Locations

The following locations will be resurfaced: 
  • Blue Bird Hall
  • Canyon Lake Drive North (from Vacation Drive to Goetz Road)
  • Canyon Lake Golf & Country Club
  • Diamond Point Park
  • Eastport Park
  • Equestrian Center Driveway Entrance
  • Gault Field
  • Holiday Harbor Park
  • Indian Beach
  • Lodge/Tennis/Sunset Beach
  • Moonstone Beach
  • North Ski East & West
  • Operations Yard
  • Senior Center
  • Sierra Park

Project Background

In 2012-13, the Canyon Lake POA entered into a $7,800,000 paving project which involved the majority of the roads within the community. That project did not include resurfacing any of the 15 parking lots within the community, Happy Camp, or Canyon Lake Drive North, east of Vacation Drive. Happy Camp was completely repaved during the Campground Renovation Project. However, the rest of these areas are badly in need of renovation, especially the Lodge and Country Club parking lots. The Lodge project will feature a new concrete ADA ramp and staircase down to the rental docks and walking pathway, and new retaining walls, planters, and additional parking spaces.

In 2016, Willdan Engineering was contracted to put together a set of bid documents for these remaining areas. They were tasked with evaluating each area for ADA compliance, and possible expansion and reconfiguration in order to create the maximum available parking spaces in each area. Further, they were asked to evaluate each area for effective drainage and to incorporate other features suggested by the community members and staff.