Golf Course Lake Renovation

The Canyon Lake POA has started the renovation of the badly leaking lake near hole 13 at the golf course.  The anticipated scope of work includes re-configuring the lake so it has natural sloping sides, adding a liner, and relocating and replacing the bridge with an earthen bridge. The new lake will save the Canyon Lake POA over $80,000 a year on its water bill!  The new slightly smaller lake will continue to remain a signature element of the course on hole 13. This project was approved by the Canyon Lake POA Board in September 2019. 

Project Photo Album 

Golf Course Lake Renovation

Project Updates

  • February 26, 2020
    Demolition has begun to reconfigure the golf course lake. The project is expected to be completed within 12 weeks. 
  • August 26, 2019
    Combined RFI Posted
  • July 30, 2019
    Project RFP Posted - Closes August 29, 2019