Posted on: November 6, 2019

Pavement Project

Country Club_10.18.2019

Project Updates

  • October 25, 2019
    The Country Club parking lot repavement is now complete. The parking lot was reconfigured and repaved. There is now a new more efficient layout with accessible parking near the entrance. New decorative stamped concrete was added to the Country Club entry and drive circle. New LED parking lot lights were also installed.
  • September 23, 2019
    - Project started with setup at East Port Park. 
  • August 2019
    - Final vendor selected
    - Board approved funding for this project in an amount not to exceed $3,425,000
  • July 2019
    - Request for Proposal closed, three bids received ranging from $3,400,000 to $4,600,000
  • June 2019
    - Request for Proposal Published

Project Locations

The following locations will be resurfaced: 

  • Blue Bird Hall
  • Canyon Lake Drive North (from Vacation Drive to Goetz Road)
  • Canyon Lake Golf & Country Club
  • Diamond Point Park
  • Eastport Park
  • Equestrian Center Driveway Entrance
  • Gault Field
  • Holiday Harbor Park
  • Indian Beach
  • Lodge/Tennis/Sunset Beach
  • Moonstone Beach
  • North Ski East & West
  • Operations Yard
  • Senior Center
  • Sierra Park

Visit Project Page
Facebook Twitter Email

Other News in Project & Community News

North Ski Area Access Project

North Ski Area Access

Posted on: November 6, 2019
project updates

Project Updates

Posted on: April 8, 2019