Pavement Project Update

Pavement Project Lodge - Mar. 16

Pavement Project Update

March 31

Commercial construction is considered critical infrastructure, so the Lodge parking lot work is continuing. Phase 2 started this week and due to weather delays this phase is anticipated to be completed by April 17. As a reminder, the Lodge parking lot is being split into phases with the goal of keeping portions of the parking lot open at all times. View Lodge Parking Lot Project Fact Sheet (updated)

Work will begin on Thursday, April 2 on Canyon Lake Drive from Vacation Drive to Goetz Road. Minimal traffic disruption is anticipated, please follow any posted signs.

Current Phase:
Phase 2 | Mar. 16 - Apr. 17Lodge Parking Lot Phases

PROJECT LOCATIONS

Locations In Progress

  • Canyon Lake Drive North from Vacation Drive to Goetz Road (starts April 2)
  • Lodge Parking Lot (currently on phase 2, partial lot closure)
  • Eastport Park (parking lot open)
  • Gault Field (parking lot open)
  • Indian Beach (parking lot open)
  • Moonstone Beach (parking lot open)
  • North Ski East & West (parking lot open)
  • Operations Yard (parking lot open)

Locations To Be Scheduled

  • Blue Bird Hall
  • Senior Center

Locations Completed

  • Canyon Lake Golf & Country Club (parking lot complete, landscaping in progress)
  • Diamond Point Park
  • Equestrian Center Driveway Entrance (pavement complete, landscaping in progress)
  • Holiday Harbor Park
  • Sierra Park