2022/24 Board Candidates Two of the five seats on the Canyon Lake POA Board of Directors are up for election in May 2022. The two-year terms of Joe Kamashian and Jim Barringham are ending. Below are the members who intend to run for the 2022/24 Board of Directors. Lance Phillips - View Lance's Candidate Statement (PDF) Tony Schwarzman - View [...]

Regular Session Board Meeting Notice

Join us at our next Regular Session Board Meeting on Tuesday, March 1 at 6 p.m. at the Lodge. Members may attend in person at the Lodge, join the virtual meeting through Zoom at vm.clpoa.net , or watch it live on our Facebook page, @CanyonLakePOA . Comments can be emailed [email protected] . Meeting Details Regular Session Board Meeting Tuesday, March 1 at 6 p.m. [...]

Road Reconstruction Phase 1 Update

Spray Drive and Channel Way are being worked on this week, however due to the weather paving has been postponed until tomorrow February 24 and Friday, February 25. Temporary street closed/no parking signs are posted in the work areas. As a reminder, general working hours are Monday through Friday from 7 a.m. to 5 p.m. Streets being reconstructed will be closed to vehicular and pedestrian [...]

Road Reconstruction Update - Phase 2 Starts Feb 28

Phase 1 of the Road Reconstruction started this week. The roads in Phase 1 are Channel Way Drive, Spray Drive, Windward Drive, and Steelhead Drive. This phase is on schedule to be completed by February 25. Phase 2 is on schedule to begin February 28 and the streets in Phase 2 are:  Canyon Club Drive (east end) Cross Hill Drive (south end) Widgeon Place [...]

Sierra Park North

This week the paving started on the pump track at Sierra Park North. The remainder of the park continues to be under construction, the retaining walls are complete, site grading continues and site utilities are being installed. The entire park will remain closed during construction, and is expected to be complete by July 2022. All of our active construction sites are off-limits to residents [...]

Presidents Day Hours

The Canyon Lake POA office (including Member Services) is closed on Monday, February 21 in observation of the President's Day holiday. Regular hours will resume on Tuesday, February 22. 

Roadrunner Park Restroom Update

Work is moving along at Roadrunner Park and the restrooms are anticipated to be completed mid-next month. Once the restroom is complete, we will be rehabilitating the horseshoe pits. As a reminder, please follow posted signage and remain clear of the work area. Those who enter the work area may be subject to citations and fines. Project Photos

Sierra Park North Development Update

The pump track at Sierra Park North is starting to take shape this week as our contractor continues with the construction of this much anticipated feature at this new park. The remainder of the park continues to be under construction, the retaining walls are complete, site grading continues and site utilities are being installed. The entire park will remain closed during construction, and is [...]

Road Reconstruction Phase 1 Starts Feb 14

The asphalt reconstruction project is scheduled to start Phase 1 on Monday, February 14. The roads in Phase 1 are Channel Way Drive, Spray Drive, Steelhead Drive, and Windward Drive. Temporary street closed/no parking signs will be posted in the work area 48 hours prior to work commencing. General working hours will be Monday through Friday from 7 a.m. to 5 p.m. Streets being [...]

Road Reconstruction Update

Due to some issues with shallow utilities, the streets included in Phases 1 through 3 have been modified.  Phase 1 is scheduled to begin on February 14. There are still 9 total phases in this portion of the project ( click here to view phase map ). Please disregard any phasing previously published. Phase 1 (Feb 14 - Feb 25) Channel Way Dr. Spray Dr. [...]

Happy Camp Restroom Remodel Funding Approved

At the Regular Session Board Meeting on February 1, the Board approved funding for the remodel of the restrooms at Happy Camp. Over 170 general contractors were invited to review the bid documents in December and five bids were received. The project schedule is being developed and while work is going on temporary restrooms will be brought on site to accommodate those staying at Happy Camp. [...]

Intent To Run Forms Available

Want to make a difference in your community? Consider joining our Board! Two of the five seats on our Board are up for election in May. Intent to Run forms are available now at the Canyon Lake POA Corporate office. Notice of Intent to Run forms must be returned no later than Thursday, March 3 before 3 p.m.   Visit Election Page

Sierra Park North Development Update

The retaining walls at the Sierra Park North are complete and site rough grading has begun. Drainage and underground utilities to start construction will begin next week. The pump track contractor will be on-site in early February to begin construction on the pump track. Please be sure to keep yourself and children out of the job site area. There are many inherent hazards while this site is [...]

Budget Workshop

Join us at our Budget Workshop on Tuesday, February 8 from 6 p.m. to 8 p.m. at the Lodge. At this Workshop members can participate in the Board's review and discussion of the 2022/23 preliminary Budget prepared by the Finance Committee. Members may attend in person at the Lodge, join the virtual meeting through Zoom at vm.clpoa.net or watch it live on the Canyon Lake POA Facebook [...]

Regular Session Board Meeting

Join us at our next Regular Session Board Meeting on Tuesday, February 1 at 6 p.m. at the Lodge. evening at 6 p.m. Members may attend at the Lodge, join virtually through Zoom at vm.clpoa.net , or watch it live on our Facebook page  @CanyonLakePOA . Send your comments directly [email protected] before the meeting. View Meeting Agenda

Road Reconstruction Update

The start dates for the Road Reconstruction Project have been delayed. Several factors have contributed to this delay. Due to widespread Covid-19, concrete deliveries for the replacement cross gutters have been an issue due to the lack of available truck drivers. The replacement concrete cross gutter phase will now continue through February 9. We have also encountered several issues with [...]

Sierra Park North Development Update

Work on the retaining wall at the Giant Fir end of Sierra Park North started this week. Please be sure to keep yourself and children out of the job site area. There are many inherent hazards while this site is under construction.

Roadrunner Park Restroom Update

Work is moving along at Roadrunner Park. The restroom contains its own sewer lift station as part of the design, to pump sewage from the building up to the sewer line in the street. Please follow posted signage and remain clear of the work area. Those who enter the work area may be subject to citations and fines.

Holiday Harbor Parking Lot Seal

The Holiday Harbor Parking Lot will have a seal coat applied and trailer spaces will be re-striped in their wider configuration. Due to a weather dealy, this project will take place on Wednesday, January 19 and Thursday, January 20 and during this time, the parking lot will be closed. About Sealing Initial sealing should occur within 12 months after asphalt surface is laid [...]

Sierra Park North Development Update

The majority of the largest mechanically stabilized earth retaining wall is complete at Sierra Park North and the site is starting to take its final rough graded shape. Please be sure to keep yourself and children out of the job site area. There are many inherent hazards while this site is under construction. Visit Project Page Visit Project Album

Roadrunner Park Restroom Update

Work is moving along at Roadrunner Park. A wrought iron fence will be constructed on the hillside above and behind the restroom. The restroom contains its own sewer lift station as part of the design, to pump sewage from the building up to the sewer line in the street. Please follow posted signage and remain clear of the work area. Those who enter the work area may be subject to citations [...]

Sierra Park Shade Structures

Installation of the new shade structures continues at Sierra Park and they are anticipated to be completed by the end of the month. The next part of this project will be adding shade structures at Indian Beach which is scheduled to start in March. Residents are asked to follow posted signage and remain clear of the work area. Those who enter the work area may be subject to citations and [...]

Road Pavement Project Starts Jan 10

The Road Pavement Project is scheduled to start on Monday, January 10. This initial phase will be to replace concrete cross gutters and spandrels at various locations. Damaged areas of concrete cross gutters will be thru Friday, January 21. Temporary no-parking signs will be posted in the work area 48 hours prior to work commencing. Vehicles should be parked in zones outside the area [...]

Sierra Park North Development Update

Site work and construction of the large retaining walls continue at Sierra Park North and the largest wall is finishing up. The smaller retaining wall at the other end of the park will begin after along with the grading of the site ( click here to read about the Mechanically Stabilized Earth retaining wall system we are using ). To avoid supply chain issues and delays, an alternate [...]

Holiday Harbor Parking Lot Seal

The Canyon Lake POA is looking for a weather window to do a seal coat on the Holiday Harbor parking lot. Should the weather be warm enough within the next couple of weeks dates will be scheduled the parking lot will be closed for two days to complete the seal. Notices will be posted on the Canyon Lake POA Facebook page and Project News page.

Sierra Park Shade Structures Update

Installation of the new shade structures continues at Sierra Park. The walk way around the playground will be poured on Monday, January 10. The green roof trim color will ultimately be updated to match the blue roof. The park remains open during work however, residents are asked to follow posted signage and remain clear of the work area. Those who enter the work area may be subject to [...]

Yoga Classes Cancelled

Restorative Yoga classes on Thursdays are cancelled for the next two weeks. Classes will resume on Thursday, January 20. Interested in joining a yoga class? This is a great body mindful class that helps you slow down, relax, and connect with your body. Classes are Thursdays at 7 p.m. a the Lodge. A six class punch card is $36 and a seven class punch card is $40, punch cards may be purchased [...]

Happy Camp Restroom RFP

The Canyon Lake POA is requesting bids to renovate the 40-year-old restroom building at Happy Camp. Bids are due by January 21, 2022. Visit www.canyonlakepoa.com/happycamprestroom to download the bid package and view project details.

Canyon Lake POA Holiday Hours

We hope that everyone has a very wonderful holiday season! Below are our modified holiday hours.  Canyon Lake POA Office December 24 to December 27 - Closed December 31 - Closed | January 1 - Closed Lighthouse Restaurant & Bar December 24 to December 28 - Closed December 31 - 4 p.m. to 9 p.m. | January 1 - Closed Week of January [...]

Sierra Park North Development Update

Site work and construction of the large retaining walls continues at Sierra Park North (click here to read about the Mechanically Stabilized Earth retaining wall system we are using ). To avoid supply chain issues and delays, an alternate mechanically stabilized wall manufacturer was chosen, also reducing our costs to build this park. Please keep yourself and children out of the jobsite [...]