pavement improvement project - Year 3

Third phase of the multi-year road rehabilitation program · Complete
Years 1
 
2
 
3
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
11
 
12

 
Year 3 is complete.

Year 3 of the pavement improvement program is complete, continuing efforts to bring Canyon Lake's 37 miles of private roads to good condition.

Year 3 Pavement Map

Year 3

Year 3 Roads

Big Butte Dr Cinnamon Teal Dr
Black Duck Dr Emperor Dr
Blackhorse Dr Golden Gate Dr
Buck Tail Dr Sorrel Ln

Year 3 Outcomes

Complete
$3,386,334
board-approved funding
37 mi
total roads managed
$6,692,140
road reserve balance

The Canyon Lake POA successfully completed Year 3 of the pavement improvement program. This phase included pavement removal and replacement, curb and gutter repairs, subgrade preparation, asphalt paving, and slurry sealing — continuing the multi-year effort to bring all 37 miles of private roads up to good condition and sustain their maintenance at that level.

Year 3 Funding

Complete
Board-approved Funding
$3,386,334
Includes 2.5% contingency
Approval Date
Jul 1, 2025
Regular Session Board Meeting
Road Reserve Fund $3,386,334
Remaining Road Reserve Balance $6,692,140

The Board approved Year 3 funding at the July 1, 2025 Regular Session Board Meeting. This project went to bid in May 2025. Each year the Canyon Lake POA Board contributes to the Road Reserve to continually maintain Canyon Lake's 37 miles of privately owned roads — the Canyon Lake POA's largest asset and maintenance liability.

Scope of Work

Pavement removal & replacement
Curb & gutter repairs
Subgrade preparation
Asphalt paving & slurry sealing
Traffic striping & markings
Pavement markers restored