2025 Pavement Improvement Project
2025 Pavement Project Overview
The Canyon Lake POA is moving forward with the third phase of its multi-year pavement improvement program.
This year's project will continue rehabilitation efforts across selected streets, including pavement removal and replacement, curb and gutter repairs, subgrade preparation, asphalt paving, and slurry sealing. Traffic striping, pavement markings, and markers will also be restored to match existing layouts.
The overall goal remains to raise the pavement condition index of Canyon Lake's 37 miles of private roads to a good condition and maintain them at that level for the long term.
2025 Pavement Project Phase Map
Click here to see when your street will be reconstructed
Project Information
Project Funding
2025 Project Funding
The Canyon Lake POA Board approved funding in the amount of $3,386,334.57 and a 2.5% contingency from the Road Reserves Fund for this project at the July 1, 2025, Regular Session Board Meeting. This project went to bid in May 2025 (click here to view the bid package). The current balance of the Canyon Lake POA's Road Reserve funds is $6,692,140.
Each year, the Canyon Lake POA Board contributes more money to the Road Reserve funds for the purpose of continually maintaining our 37 miles of privately owned roads. The roads are the Canyon Lake POA's largest asset and maintenance liability.
Project Documents
2025 Project Documents
Project RFP (Closed)
2025 Project Bid Details
On May 30, 2025 the Canyon Lake POA put out the Year 3 Pavement Improvement Project RFP with a closing date of June 24, 2025.